Client Background
Hellingly Primary School, located in East Sussex, is a well-established educational facility committed to the safety and wellbeing of its pupils, staff, and visitors. With an ageing fire alarm system in place, the school required a full upgrade to meet current fire safety standards and provide improved protection across the premises.
Project Overview
AJ Taylor was appointed to carry out the complete removal of the school’s existing conventional fire alarm system and install a modern, addressable two-loop fire detection system. The new system was designed to meet a Category L2 standard—ensuring early detection and warning throughout critical areas of the building.
Execution
To minimise disruption, all work was carried out during the Easter school holidays, allowing our team to complete the full upgrade within just 9 working days.
The new system included:
- Installation of an MX5 Pro fire alarm control panel and a secondary repeater panel.
- Integration of Apollo XP95 addressable devices throughout the building, enhancing pinpoint detection and zone accuracy.
- Connection of the fire alarm to the school’s access control system, ensuring all access-controlled doors automatically fail safe and open in the event of an alarm.
- Interface with any on-site mechanical life safety systems for seamless emergency coordination.
- All wiring was completed using fire-protected FP200 cable, with a dedicated 13A unswitched fused connection unit providing power to the system.
Result
The newly installed addressable L2 fire detection system now provides enhanced fire safety coverage throughout Hellingly Primary School. Staff benefit from clearer, more responsive alerts, while the integration with access control and life safety systems provides peace of mind that the building is fully protected in the event of an emergency.
AJ Taylor delivered the project on time and with minimal disruption, reaffirming our reputation as a trusted specialist in fire safety systems for the education sector.