Client Background
East Grinstead Library is a well-used public facility managed by West Sussex County Council (WSCC), providing vital educational and community services. As part of an ongoing effort to modernise public buildings and improve energy efficiency, the library underwent a full lighting upgrade, with additional improvements made to site security.
Project Overview
AJ Taylor was appointed by WSCC to carry out a full lighting replacement throughout East Grinstead Library, alongside the installation of a new CCTV system. The project aimed to enhance lighting quality, improve energy efficiency, and increase overall security across the site.
In addition to electrical works, AJ Taylor was also designated Principal Contractor, responsible for managing site-wide health and safety compliance, including the coordination of subcontractors working on ceiling tile replacement.
Execution
Lighting Installation:
The lighting upgrade featured new LED light fittings supplied by Dextra Lighting, including a mix of 600×600 LED panels and linear luminaires.
- The upper floor (main library) was fitted primarily with linear lighting, requiring modifications to the existing wiring to accommodate new layouts and fixture positions.
- The lower floor saw a combination of fittings, again requiring rewiring and adjustments to suit new lighting locations.
- All non-public areas were also upgraded with new LED lighting to maintain consistency throughout the building.
CCTV System Installation:
While works were underway, the client enquired about CCTV installation. AJ Taylor’s Fire & Security department provided a quote and carried out the full installation of CCTV systems alongside the lighting works, minimising disruption and improving project efficiency.
Principal Contractor Role:
As Principal Contractor, AJ Taylor coordinated all site health and safety documentation, including:
- The Construction Phase Plan
- Risk assessments and method statements
- Coordination of documentation from other contractors (e.g., ceiling tile replacement teams)
Minimising Disruption:
- The first floor remained operational during phased installation works, using barriers and signage to maintain safe public access.
- For ground floor works, a temporary full closure was programmed and completed ahead of schedule.
- Final works were completed in non-public areas with minimal impact to operations.
Result
The project was delivered on time and to specification, with all lighting and CCTV works completed seamlessly under AJ Taylor’s management.
✅ Improved lighting levels throughout the library were well-received, especially important in a reading-focused environment.
✅ The new CCTV system enhanced on-site security and visibility.
✅ The client was pleased with both the outcome and project delivery, and the building reopened ahead of schedule after necessary closures.
📍 Location: East Grinstead, West Sussex
🔧 Services: LED Lighting Installation, CCTV System Installation, Principal Contractor Duties
🏛 Sector: Public Sector / Local Authority