Client Background
Adur District Council appointed AJ Taylor to deliver a high-performance solar PV and battery storage solution at Wadurs Swimming Pool in Sussex. With rising energy costs and a strong commitment to sustainability, the council sought to reduce the site’s carbon footprint and operating costs while improving energy resilience.
Project Overview
This large-scale renewable energy project involved the installation of a 75.69kW Solar PV system alongside Tesla Powerwall battery storage to harness solar energy throughout the day and reduce reliance on grid electricity during peak hours and darker months.
The system was designed to power the energy-intensive swimming facility while supporting the council’s broader decarbonisation goals.
Execution
The installation took place between 17th and 28th October 2025, beginning with the erection of scaffolding, including a bridge system to access the flat roof.
Key Components Installed:
- 146 Longi Hi-MO6 Explorer 435W mono solar panels on pitched biscuit tile roofs (facing East, South & West) using the Renusol on-roof mounting system
- An additional 28 solar panels mounted on a flat roof using Van der Valk mounting system, secured with pre-calculated 9kg concrete weights
- 2″ galvanised traywork mounted on rubber feet for safe, non-penetrative cable routing
- SolarEdge 75.69kW DC system, with a maximum 55.80kW AC output, including module-level power optimisers for enhanced performance, safety, and monitoring
- SolarEdge Firefighter Gateway for emergency rapid shutdown capability
- Bird protection spikes for panel safeguarding and aesthetic finish
To ensure year-round energy support, three Tesla Powerwalls (total capacity of 40.5kWh) were installed. These provide overnight and backup power from stored solar energy and can be configured to charge from the grid during off-peak hours for additional savings.
Result
- Significant Energy Savings: The system offsets a large portion of the site’s energy needs, especially during peak daylight hours.
- Carbon Reduction: A considerable drop in CO₂ emissions aligns with Adur Council’s sustainability objectives.
- 24/7 Monitoring & Maintenance: The SolarEdge platform allows the council to track the performance of each panel and battery in real time and identify any maintenance needs early.
- Enhanced Safety: SolarEdge’s SafeDC™, module-level shutdown, arc fault detection, and UK-compliant safety systems offer industry-leading protection for users and first responders.
- Energy Independence: The Tesla Powerwall batteries reduce reliance on the grid, improve energy security, and allow for smart, low-cost charging cycles.
Technology in Action
This project showcases how solar PV and battery storage can be used to future-proof public sector buildings against energy price volatility and environmental targets. With AJ Taylor’s in-house design and specialist installation team, Wadurs Swimming Pool is now a model of how renewables can be successfully integrated into community infrastructure.